Our Timeline is Everything!

Scope: 14,948 SF, 16 unit, ground up building with parking spaces, backyard, and roof deck.

Project Timeline

0/00/0000

Day 1

Preconstruction Occurs prior to Closing.

2/28/2022

Day 1

Acquisition Closing - Capital partners go in.

3/20/2022

1st month

Demolition of prior building starts.

9/9/2022

6th  month

Superstructure Topped out.
Exterior wall & plumbing
in progress.

3/21/2023

13thmonth

Building Exterior 100% completed. Interior's are 80% completed.

5/2/2023

14th month

Marketing has started online.

5/2/2023

14thmonth

Listed by Corcoran $1,665,000

5/23/2023

20 DOM

In Contract, Full Ask $1,665,000

8/14/2023

18thmonth

15 of 16 units in contract within 90 days. TCO received and closings are being scheduled.

9/7/2023

19thmonth

First Closing Occured. 8 of the 16 units are closed within 30 days

11/27/2023

21th month

Projected Completed

Units 9-15 are closed in next 30 days. All units average 22% higher Price/sqft then market competitors with less Days on Market

Our Timeline is Everything!

Scope: 14,948 SF, 16 unit, ground up building with parking spaces, backyard, and roof deck.

Project Timeline
Preconstruction Occurs prior to Closing.
2/28/2022
Day 1
Acquisition Closing - Capital partners go in.
3/20/2022
1st month
Demolition of prior building starts.
9/9/2022
6th  month
Superstructure Topped out.Exterior wall & plumbing in progress.
3/21/2023
13th month
Building Exterior 100% completed. Interior's are 80% completed.
5/2/2023
14th month
Marketing has started online.
5/2/2023
14th month
Listed by Corcoran $1,665,000
5/23/2023
20 DOM
In Contract, Full Ask $1,665,000
8/14/2023
18th month
15 of 16 units in contract within 90 days. TCO received and closings are being scheduled.
9/7/2023
19th month
First Closing Occured. 8 of the 16 units are closed within 30 days
11/27/2023
21st month

Project Completed
Units 9-15 are closed in next 30 days. All units average 22% higher Price/sqft then market competitors with less Days on Market